Projects & Delivery

Projects & Delivery Portfolio

Portfolio-wide governance across 14 active construction projects ($86.4M live sum).

Portfolio Completion
82.4%3.6% Schedule Gap

Target: 86.0% Baseline

Overall Progress82.4%
Live Contract Sum
$86.4M+8.4% YoY

14 Active Projects

Milestones at Risk
3 ProjectsCritical Path Lag

Bayside, Orion & Westport

Projects Over Budget
3 JobsBayside $388k Over

Forecast Exposure: $611k

+$611,000 Exp.Budget Variance
Critical Compliance Actions
4 ActionsSafeWork Victoria

2 EWP Licences + Temp Power

Forecast Margin Variance
-$611,000-1.4% Net Drag

Net Margin Impact

C-2417Critical
$18.6M

Bayside Medical Centre

Bayside Health Alliance · Lead: Maya Collins

Project Completion68%
7d Delayed+$388,000 over
Level 4 services rough-in (18 September)
C-2432Healthy
$24.1M

Northbank Logistics Hub

Northbank Industrial · Lead: James Patel

Project Completion44%
+2d AheadOn budget
Structural steel completion (23 September)
C-2398Watch
$12.7M

Westport Civic Works

Westport City Council · Lead: Amelia Ross

Project Completion91%
3d Delayed+$76,000 over
Practical completion (30 September)
C-2451Healthy
$31M

Orion Data Centre, Stage 2

Orion Cloud Infrastructure · Lead: Noah Chen

Project Completion23%
On programmeOn budget
Basement slab pour (16 September)
C-2426Watch
$9.8M

Kestrel Education Precinct

Victorian Learning Authority · Lead: Ruby Fernandez

Project Completion76%
1d Delayed+$147,000 over
Joinery installation (20 September)

Autonomous Agent Observations

Live cross-system synthesis from site diaries, Procore, and Business Central

  • Bayside Medical CentreServices coordination delayMonitored
  • Bayside Medical CentreLate switchboard approvalMonitored
  • Bayside Medical CentreUnsubmitted EOT evidenceMonitored
  • Bayside Medical CentreUnapproved variationsMonitored
  • Northbank Logistics HubStructural steel delivery on trackMonitored
  • Northbank Logistics HubFull crew coverageMonitored
  • Westport Civic WorksDefect close-out blockersMonitored
  • Westport Civic WorksMissing consultant approvalMonitored
  • Westport Civic WorksIncomplete O&M manualsMonitored
  • Orion Data Centre, Stage 2Crew confirmed for concrete pourMonitored
  • Orion Data Centre, Stage 2Favourable cost varianceMonitored
  • Kestrel Education PrecinctJoinery productivity varianceMonitored
  • Kestrel Education PrecinctCommissioning delay riskMonitored
  • Kestrel Education PrecinctCompliance documents expiringMonitored